Unipro PJSC (E.ON Russia JSC until June 2016) is the most efficient company of the thermal power generation sector in the Russian Federation. Unipro PJSC consists of five heat power plants with the total capacity of 11,285 MW: Surgutskaya GRES-2 (5,667.1 MW), Berezovskaya GRES (2,420 MW), Shaturskaya GRES (1,500 MW), Smolenskaya GRES (630 MW) and Yaivinskaya GRES (1,048 MW).

Company’s core operations comprise electric power and capacity generation and sales. Unipro PJSC is operating at the Russian market of distributed generation and engineering as well.

In 2005, OGK-4 OJSC was established on the basis of five power plants of 8,630 MW: Surgutskaya GRES-2, Berezovskaya GRES, Shaturskaya GRES, Smolenskaya GRES and Yaivinskaya GRES.

On April 25, 2023, the President of the Russian Federation signed Decree No. 302, according to which 83.73% of the shares of Unipro PJSC owned by the Uniper SE concern are transferred to the interim administration of the Federal Agency for State Property Management (Rosimushchestvo).

In 2010-2011, the Company put into operation 4 new combined cycle power units with the total capacity of 1,600 MW at Surgutskaya GRES-2, Shaturskaya GRES and Yaivinskaya GRES, and increased the capacity of Berezovskaya GRES by 100 MW due to the equipment modernization. After the commissioning of a coal-fired power unit of 800 MW at Berezovskaya GRES in 2015, E.ON Russia (Unipro PJSC since June 2016) completed its investment program, having increased the total installed capacity by 2,400 MW.

In 2016, due to remarking of 800MW STU power units, Surgutskaya GRES-2 has officially obtained the aggregate extra-power of 60 MW.

In 2017, at Yaivinskaya GRES Branch upgrade of the gas turbine of power unit No.5 of PGU-400 was carried out in order to increase the installed power by 24 MW.

In 2019 Surgutskaya GRES-2 increased the capacity of CCGT Power Unit No.8 by 10 MW.
Five SPU power units were selected to participate in the modernization program. Modernization of power unit No.1 STU-810 MW of Surgutskaya GRES-2 ended in 2022, thus the unit capacity reached 830 MW.

In 2023 unit No.3 increased its capacity to 820 MW.

Thus, as a result of the construction of new facilities and the implemented modernization program, currently the total installed capacity of Unipro PJSC is 11,285.1 MW.

 

Production

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

Electricity generation
bln
kWh

62,467

64,202

62,995

59,238

53,766

54,530

48,243

46,649

46,433

41,746

45,234

53,955

56,547

ICUF
%

73.60

70.70

69.50

65.40

58.00

55.4

49.1

47.4

47.2

42.3

45.9

54.7

57,2