Smolenskaya GRES Supplies Heat to the Settlement of Ozerny

Smolenskaya GRES Branch of Unipro PJSC starts the heating season in Ozerny, pursuant to the order of the Ozerny Urban Settlement Administration. 

Kindergartens and the school were connected on a first-priority basis. The residential sector was connected in stages, following the approved schedule.

Power engineers have completed a large scope of work to prepare heating networks for the winter season of 2022–2023. Pipelines were replaced: 530 mm diameter (244 linear meters) on Lenin Street, and 273 mm diameter (348 linear meters) on Koltsevaya Street. 108 mm diameter pipeline (100 linear meters) on Koltsevaya Street was repaired. Current repairs have been performed on Power Units 1 and 2, and major repairs are underway on Power Unit 3.

Smolenskaya GRES supplies heat to more than 2,800 consumers in the village of Ozerny. The total length of the main and district heat supply systems within the area of responsibility of the Branch amounts to more than 34 km.